Works in Cerro Grande advance satisfactory

The construction works of the wind farm are advancing at a good pace. Last week, the works to improve the external and internal access roads to the wind farm finished; Furthermore, the workers could move to and  work from the containers installed and equipped for office purposes.
Regarding the construction works and installation of the wind converters, 6 foundations of turbines located in the first row are completed. Concrete segments produced in the plant installed in Tacuarembó keep arriving every week.