First concrete segments arrive to Cerro Grande
Last week the first concrete segments were delivered to Cerro Grande Wind Farm. This first shipment was done in several days in which 21 segments were delivered in convoys of 2 trucks each.
From now on, it is expected to organize a weekly delivery of segments until the end of this year. This week the shipment of 25 segments more took place, reaching the amount of 46 segments already allocated in site.
The segments are placed on the wind turbine’s platforms as well as in a specifically reserved store area before their final destination.
It is expected to ship weekly about 27 segments, the equivalent to one and a half tower.